Structural reinforcement

Production of reinforced structures. Fiber reinforced polimer lamelle, fiber reinforced polimer plate, reinforcing with a steel elements.

Our workers are trained by the manufacturer ”Sika” and they are certified for installation of ”Sika” products.

Development projects of strengthening which include the structural require testing and structural analysis. We have years of experience in these matters.


GALLERY

Completed projects

  • Period 2020

    HEP Prozvodnja d.o.o., Pogon TE-TO Zagreb, Croatia

    Reinforcement of the top of the chimney made of brick in TE-TO Zagreb with carbon fiber fabric (CFRP).
    Contracting authority: HEP Prozvodnja d.o.o., Pogon TE-TO Zagreb, Croatia, 2020.

  • Period 2017

    JP Elektroprivreda BiH d.d. - Termoelektrana Tuzla, Bosnia and Herzegovina

    Static strengthening of reinforced concrete natural cooling tower RT-1, H=62m with carbon strips (CFRP).
    Contracting authority: JP Elektroprivreda BiH d.d. - Termoelektrana Tuzla, Bosnia and Herzegovina, 2017.

  • Period 2014

    Power plant Kakanj, Bosnia and Herzegovina

    Design and construction reinforcement of chimney- making of reinforced concrete ring due to enlargement opening of flue gas ducts in works of reconstruction and repair of chimney H=100m.
    Contracting authority: Electricity company FBiH. Power plant Kakanj, Bosnia and Herzegovina, 2014.

  • Period 2012

    Power plant Tuzla, Bosnia and Herzegovina

    Static strengthening of reinforced concrete chimney unit 6, h = 165m with carbon blades with inside and outside.
    Contracting authority: Electricity company FBiH. Power plant Tuzla, Bosnia and Herzegovina, 2012.

  • Period 2011

    ”Natron-Hayat” d.o.o. Maglaj, Bosnia and Herzegovina

    Static strengthening top of masonry chimney h = 100m carbon blades within the repair works.
    Contracting authority: ”Natron-Hayat” d.o.o. Maglaj, Bosnia and Herzegovina.

  • Period 2009

    Power plant ”Oslomej” Kicevo, Macedonia

    Static strengthening of reinforced concrete chimney h = 180m carbon screens within the repair works.
    Contracting authority: Power plant ”Oslomej” Kicevo, Macedonia, 2009.

  • Period 2007

    Power plant Tuzla, Bosnia and Herzegovina

    Static strengthening top of reinforced concrete chimney unit 5, h = 100m, with carbon lamellas.
    Contracting authority: Electricity company FBiH. Power plant Tuzla, Bosnia and Herzegovina, 2012.

  • Period 2006

    Toplane Banja Luka, Bosnia and Herzegovina

    Static strengthening foundation of steel chimney h = 60m with carbon screens.
    Contracting authority: The joint stock company Toplane Banja Luka, Bosnia and Herzegovina, 2006.